| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 Aug 2024 | 100 % COMPLETED.Final bill submitted | Kollam WS Sn 1 - AE | |
| 12 Aug 2024 | 79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED | Kollam WS Sn 1 - AE | |
| 09 Aug 2024 | 79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED | Kollam WS Sn 1 - AE | |
| 07 Aug 2024 | 79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED | Kollam WS Sn 1 - AE | |
| 05 Aug 2024 | 79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED | Kollam WS Sn 1 - AE | |
| 01 Aug 2024 | 79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED | Kollam WS Sn 1 - AE | |
| 29 Jul 2024 | 79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED | Kollam WS Sn 1 - AE | |
| 25 Jul 2024 | 79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED | Kollam WS Sn 1 - AE | |
| 22 Jul 2024 | 79 % COMPLETED, 279 NOS. OF TAP DISCONNECTED | Kollam WS Sn 1 - AE | |
| 18 Jul 2024 | 60 % COMPLETED, 200 NOS. OF TAP DISCONNECTED | Kollam WS Sn 1 - AE |