| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 29 Aug 2021 | Work is under progress | Kottarakkara PH Dn EE | |
| 23 Aug 2021 | Work is going on | Kottarakkara PH Dn EE | |
| 13 Aug 2021 | Pipe laying work started | Kottarakkara PH Dn EE | |
| 05 Aug 2021 | Work just started | Kottarakkara PH Dn EE | |
| 24 Jul 2021 | Work started and pipe supplied for connection and specials not supplied | Kottarakkara PH Dn EE | |
| 20 Jul 2021 | Work Started. Pipe not supplied | Kottarakkara PH Dn EE | |
| 06 Jul 2021 | Agreement executed. | Kottarakkara PH Dn EE | |
| 12 Jun 2021 | Work delayed due to lock down from 8.5.2021 to16/06/2021 | Kottarakkara PH Dn EE | |
| 03 Jun 2021 | Work delayed due to lock down from 8.5.2021 to9/06/2021 | Kottarakkara PH Dn EE | |
| 28 May 2021 | Work delayed due to lock down from 8.5.2021 to 30.5.2021 | Kottarakkara PH Dn EE |