| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Mar 2022 | 1370 FHTC's provided. Line extension work in progress. | Kottarakkara PH Dn EE | |
| 14 Feb 2022 | 1290 FHTC's provided. Line extension work in progress. | Kottarakkara PH Dn EE | |
| 09 Feb 2022 | 1250 FHTC's provided. Line extension work in progress. | Kottarakkara PH Dn EE | |
| 03 Feb 2022 | 1202 FHTC's provided. Line extension work in progress. | Kottarakkara PH Dn EE | |
| 03 Feb 2022 | 1153 FHTC's provided. GLSR plastering and concrete work in progress | Kottarakkara PH Dn EE | |
| 01 Feb 2022 | 1152 FHTC's provided. GLSR plastering and concrete work in progress | Kottarakkara PH Dn EE | |
| 27 Jan 2022 | 1080 FHTC's provided. GLSR plastering and concrete work in progress | Kottarakkara PH Dn EE | |
| 22 Jan 2022 | 980 FHTC's provided. GLSR plastering and concrete work in progress | Kottarakkara PH Dn EE | |
| 07 Jan 2022 | 912 FHTCS provided and work in progress | Kottarakkara PH Dn EE | |
| 01 Jan 2022 | 892 FHTC's provided in various wards of Ezhukone panchayath. | Kottarakkara PH Dn EE |