| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 26 Mar 2023 | Ward: 12-Inter connection works is going on. Ward:02 - Providing house connection is going on. Ward : 05- Providing house connection is going on. | Kottarakkara PH Sn - AE | |
| 25 Mar 2023 | Ward: 12-Inter connection works is going on. Ward:02 - Providing house connection is going on. Ward : 05- Providing house connection is going on. | Kottarakkara PH Sn - AE | |
| 24 Mar 2023 | Ward: 12- Laying 50 mm PVC Pipes is going on. Ward:02 - Providing house connection is going on. Ward : 05- Providing house connection is going on. | Kottarakkara PH Sn - AE | |
| 23 Mar 2023 | Ward: 12- Laying 50 mm PVC Pipes is going on. Ward:2 - Providing house connection is going on. | Kottarakkara PH Sn - AE | |
| 22 Mar 2023 | Ward: 12- Laying 50 mm PVC Pipes is going on. Ward:2 - Providing house connection is going on. Ward:5- Providing house connection is going on. | Kottarakkara PH Sn - AE | |
| 21 Mar 2023 | Ward: 12- Laying 50 mm PVC Pipes is going on. Ward:2 - Providing house connection is going on. | Kottarakkara PH Sn - AE | |
| 20 Mar 2023 | Ward: 10- Laying 50 mm PVC Pipes is going on. Ward:2 - Providing house connection is going on. Ward No : 01 - Restoration of concrete road is going on. | Kottarakkara PH Sn - AE | |
| 19 Mar 2023 | Ward: 10- Laying 50 mm PVC Pipes is going on. Ward:2 - Providing house connection is going on. | Kottarakkara PH Sn - AE | |
| 18 Mar 2023 | Ward: 10- Laying 50 mm PVC Pipes is going on. Ward:2 - Providing house connection is going on. | Kottarakkara PH Sn - AE | |
| 17 Mar 2023 | Ward: 10- Laying 50 mm PVC Pipes is going on. Ward:2 - Providing house connection is going on. | Kottarakkara PH Sn - AE |