| 16 Apr 2023 | Ward: 07 -Laying with 90 mm PVC pipes are going on. Ward:07 -Restoration of concrete road is going on. Ward : 05- Providing house connection is going on, Ward No:01-Providing house connection is going on, Ward no:12 - Providing house connection is going on. | Kottarakkara PH Sn - AE | |
| 15 Apr 2023 | Ward: 07 -Laying with 90 mm PVC pipes are going on. Ward:07 -Restoration of concrete road is going on. Ward : 05- Providing house connection is going on, Ward No:01-Providing house connection is going on, Ward no:12 - Providing house connection is going on. | Kottarakkara PH Sn - AE | |
| 14 Apr 2023 | Ward: 07 -Laying with 90 mm PVC pipes are going on. Ward:07 -Restoration of concrete road is going on. Ward : 05- Providing house connection is going on, Ward No:01-Providing house connection is going on, Ward no:12 - Providing house connection is going on. | Kottarakkara PH Sn - AE | |
| 13 Apr 2023 | Ward: 07 -Laying with 90 mm PVC pipes are going on. Ward:07 -Restoration of concrete road is going on. Ward : 05- Providing house connection is going on, Ward No:01-Providing house connection is going on, Ward no:12 - Providing house connection is going on. | Kottarakkara PH Sn - AE | |
| 12 Apr 2023 | Ward: 07 -Laying with 90 mm PVC pipes are going on. Ward:07 -Restoration of concrete road is going on. Ward : 05- Providing house connection is going on, Ward No:01-Providing house connection is going on, Ward no:12 - Providing house connection is going on. | Kottarakkara PH Sn - AE | |
| 11 Apr 2023 | Ward: 07 -Inter connection works and Laying are going on. Ward:07 -Restoration of concrete road is going on. Ward : 05- Providing house connection is going on, Ward No:01-Providing house connection is going on, Ward no:12 - Providing house connection is going on. | Kottarakkara PH Sn - AE | |
| 10 Apr 2023 | Ward: 07 -Inter connection works and Laying are going on. Ward:07 -Restoration of concrete road is going on. Ward : 05- Providing house connection is going on, Ward No:01-Providing house connection is going on, Ward no:12 - Providing house connection is going on. | Kottarakkara PH Sn - AE | |
| 08 Apr 2023 | Ward: 10-Inter connection works and Laying are going on. Ward:02 - Providing Interconnection is going on. Ward : 05- Providing house connection is going on | Kottarakkara PH Sn - AE | |
| 07 Apr 2023 | Ward: 10-Inter connection works and Laying are going on. Ward:02 - Providing Interconnection is going on. Ward : 05- Providing house connection is going on | Kottarakkara PH Sn - AE | |
| 06 Apr 2023 | Ward: 10-Inter connection works and Laying are going on. Ward:02 - Providing Interconnection is going on. Ward : 05- Providing house connection is going on | Kottarakkara PH Sn - AE |