Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Nov 2022 | work is completed billing under preparation. | Vadasserikara PH Sn - AE | |
05 Nov 2022 | 82% WORK COMPLETED | Vadasserikara PH Sn - AE | |
11 Sep 2022 | 81% WORK COMPLETED | Vadasserikara PH Sn - AE | |
21 Jul 2022 | 80% work completed | Pathanamthitta PH Dn EE | |
12 Apr 2022 | Pipe laying work in progress | Pathanamthitta PH Dn EE | |
09 Feb 2022 | Testing and supply of pipes in progress | Pathanamthitta PH Dn EE | |
04 Feb 2022 | Agreement Executed on 11/01/2022 | Pathanamthitta PH Dn EE | |
04 Feb 2022 | Work Awarded on 30/12/2021 | Pathanamthitta PH Dn EE |