Status Date |
Overall Project Status |
Project Officer |
Contact |
08 Dec 2023 |
KIIFB - Augmentation of WSS to Karumalloor and Kunnukara Panchayaths-Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase I - Package I- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package II- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package III- FS received from KIIFB is less than AS amount, No final decision received from higher Office |
Perumbavoor Project Dn AE2 |
|
04 Dec 2023 |
KIIFB - Augmentation of WSS to Karumalloor and Kunnukara Panchayaths-Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase I - Package I- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package II- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package III- FS received from KIIFB is less than AS amount, No final decision received from higher Office |
Perumbavoor Project Dn AE2 |
|
30 Nov 2023 |
KIIFB - Augmentation of WSS to Karumalloor and Kunnukara Panchayaths-Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase I - Package I- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package II- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package III- FS received from KIIFB is less than AS amount, No final decision received from higher Office |
Perumbavoor Project Dn AE2 |
|
24 Nov 2023 |
KIIFB - Augmentation of WSS to Karumalloor and Kunnukara Panchayaths-Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase I - Package I- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package II- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package III- FS received from KIIFB is less than AS amount, No final decision received from higher Office |
Perumbavoor Project Dn AE2 |
|
17 Nov 2023 |
KIIFB - Augmentation of WSS to Karumalloor and Kunnukara Panchayaths-Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase I - Package I- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package II- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package III- FS received from KIIFB is less than AS amount, No final decision received from higher Office |
Perumbavoor Project Dn AE2 |
|
16 Nov 2023 |
KIIFB - Augmentation of WSS to Karumalloor and Kunnukara Panchayaths-Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase I - Package I- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package II- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package III- FS received from KIIFB is less than AS amount, No final decision received from higher Office |
Perumbavoor Project Dn AE2 |
|
15 Nov 2023 |
KIIFB - Augmentation of WSS to Karumalloor and Kunnukara Panchayaths-Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase I - Package I- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package II- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package III- FS received from KIIFB is less than AS amount, No final decision received from higher Office |
Perumbavoor Project Dn AE2 |
|
14 Nov 2023 |
KIIFB - Augmentation of WSS to Karumalloor and Kunnukara Panchayaths-Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase I - Package I- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package II- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package III- FS received from KIIFB is less than AS amount, No final decision received from higher Office |
Perumbavoor Project Dn AE2 |
|
13 Nov 2023 |
KIIFB - Augmentation of WSS to Karumalloor and Kunnukara Panchayaths-Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase I - Package I- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package II- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package III- FS received from KIIFB is less than AS amount, No final decision received from higher Office |
Perumbavoor Project Dn AE2 |
|
12 Nov 2023 |
KIIFB - Augmentation of WSS to Karumalloor and Kunnukara Panchayaths-Augmentation of WSS to Karumallur and Kunnukara Panchayaths - Phase I - Package I- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package II- FS received from KIIFB is less than AS amount, No final decision received from higher Office, Phase I - Package III- FS received from KIIFB is less than AS amount, No final decision received from higher Office |
Perumbavoor Project Dn AE2 |
|