Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
31 May 2021 | Package 1-Alternate land for 6 LL Sump handed over by Panoor Municipality , Package 2- Application for land acquisition of alternate land (for 24 LL GLSR) submitted and under processing | Mattannur Project Sn 2 AE | |
21 May 2021 | Application for land acquisition of alternate land (for 24 LL GLSR) submitted and under processing | Mattannur Project Sn 2 AE | |
28 Apr 2021 | Application for land acquisition of alternate land (for 24 LL GLSR) submitted and under processing | Mattannur Project Sn 2 AE | |
14 Apr 2021 | Application for land acquisition of alternate land (for 24 LL GLSR) submitted and under processing | Mattannur Project Sn 2 AE | |
18 Mar 2021 | Application for land acquisition of alternate land (for 24 LL GLSR) submitted | Mattannur Project Sn 2 AE | |
07 Mar 2021 | Application for land acquisition of alternate land submitted to Dist Collector on 5/2/21 | Mattannur Project Sn 2 AE | |
24 Feb 2021 | Application for land acquisition of alternate site submitted to Dist collector on 5/2/21 | Mattannur Project Sn 2 AE | |
24 Feb 2021 | Application submitted to Dist.Collector for land Acquisition on 05/02/2021 | Mattannur Project Sn 2 AE | |
19 Feb 2021 | Land Acquisition not completed | Mattannur Project Sn 2 AE | |
09 Feb 2021 | Application submitted to Dist.Collector for land Acquisition on 05/02/2021 | Mattannur Project Sn 2 AE |