KIIFB WRD 025-15 THALASSERY-KOOTHUPARAMBA COMPREHENSIVE DRINKING WATER PROJECT

Project KIIFB WRD 025-15 THALASSERY-KOOTHUPARAMBA COMPREHENSIVE DRINKING WATER PROJECT
Project Code KNRKIIFB1118611
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Gravity main from Myladi to Kanakamala Sump (700mm DI K9 - 19280m & 600mm DI K9 -11335m) , 6LL sump cum pump house, CWPS- 98 HP C/F pumpset – 3 Nos, Transformer , 15 LL OHSR at Kariyad, 13 LLOHSR at Chokli 24 LL GLSR at Kanakamala, GM from GLSR Kanakamala to OHSR at Chokli (400mm DI K9 - 1490m (common) & 300mm DI K9 - 2980m) and 250mm DI K9- 2790m to OHSR at Kariyad. Pumping main 500mm DI K9 - 160m (from Kanakamala sump to Kanakamala tank)
Status On-going
District Kannur
Executing Office Mattannur Project Dn
AS Amount (Rs) 858600000
AS Number WRD 025-15-PA-01
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs) 5187509
Total Bill Paid (Rs) 5187509
Population Benefitted 207983
Capacity in MLD 36.00
Actual Project Completion Date Date is not specified
Coverage Panoor Municipality, Chokli, Mangattidam,panniyannur & Mokeri panchayaths

Packages

No. Project Name Location View
1 KIIFB -WRD 025-15 -THALASSERY-KOOTHUPARAMBA COMPREHENSIVE DRINKING WATER PROJECT - PACKAGE I Mattannur Project Dn
2 KIIFB -WRD 025-15 -THALASSERY-KOOTHUPARAMBA COMPREHENSIVE DRINKING WATER PROJECT- PACKAGE II Mattannur Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Oct 2023 Technical Sanction Pending. Awaiting Revalidation of Administrative Sanction by KIIFB. Mattannur Project Sn 2 AE
13 Mar 2023 Revalidation proposal submitted to Superintending Engineer, PH Circle,Kannur Mattannur Project Sn 2 AE
22 Jan 2023 Land acquisition for OHSR at Kariyad and GLSR at Kanakamala completed and land awarded. Permissive sanction obtained for the construction of OHSR at Chokli. Deviation proposal submitted. Mattannur Project Sn 2 AE
31 Jul 2022 Land acquisition nearing completion. An amount of Rs. 45 lakhs remitted to LA( Spl) Tahsildar on 13/07/2022 for LA and establishment charges. Permissive sanction obtained for the construction of 13 LL OHSR at Chokli Govt. College. Mattannur Project Sn 2 AE
06 Nov 2021 Package I- Alternate land for 6LL sump cum pump house handed over by Panoor Municipality, LA order issued by Dist.collcetor for gravity main . 19(1) notification to be published.Package II- Collector ordered for acquisition for 15 LL OHSR at Kariyad.11(1) notification issued. 19(1) notification to be issued. Permissive sanction proposal for 13 LL OHSR chokli submitted to WRD by MD on 06/07/2020 . A copy of the same is submitted by chokli govt college Principal to College education Director on 11/02/21 as per our request. Higher Education Department addressed to Government for permissive sanction with Revenue department. Application for land acquisition of alternate land (for 24 LL GLSR) submitted to District collector. Collector sought report of feasibility from Thahsildar (LA) on 16/06/21. SIS study completed .Contacted land owners for obtaining advance possession for Kanakamala tank . Mattannur Project Sn 2 AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion 31/08/2023

Processing Dates

AS Date 16 Nov 2018

Other details

Project Officers View