11 Jun 2024 The estimate is submitted and work tendered,single tender received. Hence retendered on 09/02/24 with due date 17/02/24.Agrement executed. Sasthamcotta WS Sn 2 HW - AE
07 Jun 2024 The estimate is submitted and work tendered,single tender received. Hence retendered on 09/02/24 with due date 17/02/24.Agrement executed. Sasthamcotta WS Sn 2 HW - AE
01 Jun 2024 The estimate is submitted and work tendered,single tender received. Hence retendered on 09/02/24 with due date 17/02/24.Agrement executed. Sasthamcotta WS Sn 2 HW - AE
28 May 2024 The estimate is submitted and work tendered,single tender received. Hence retendered on 09/02/24 with due date 17/02/24 Sasthamcotta WS Sn 2 HW - AE
28 May 2024 The estimate is submitted and work tendered,single tender received. Hence retendered on 09/02/24 with due date 17/02/24 Sasthamcotta WS Sn 2 HW - AE
20 May 2024 The estimate is submitted and work tendered,single tender received. Hence retendered on 09/02/24 with due date 17/02/24 Sasthamcotta WS Sn 2 HW - AE
16 May 2024 The estimate is submitted and work tendered,single tender received. Hence retendered on 09/02/24 with due date 17/02/24 Sasthamcotta WS Sn 2 HW - AE
13 May 2024 State paln 2023- 24 Supply and erection of 40HP pumpset with head 30m discharge 70lps including all accessories Sasthamcotta WS Sn 2 HW - AE
09 May 2024 The estimate is submitted and work tendered,single tender received. Hence retendered on 09/02/24 with due date 17/02/24 Sasthamcotta WS Sn 2 HW - AE
06 May 2024 The estimate is submitted and work tendered,single tender received. Hence retendered on 09/02/24 with due date 17/02/24 Sasthamcotta WS Sn 2 HW - AE