| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Feb 2024 | The estimate is submitted and work tendered,single tender received. Hence retendered on 09/02/24 with due date 17/02/24 | Sasthamcotta WS Sn 2 HW - AE | |
| 14 Feb 2024 | The estimate is submitted and work tendered,single tender received. Hence retendered on 09/02/24 with due date 17/02/24 | Sasthamcotta WS Sn 2 HW - AE | |
| 14 Feb 2024 | The estimate is submitted and work tendered,single bid received. Hence work is retendered on 09/02/24 | Sasthamcotta WS Sn 2 HW - AE | |
| 13 Feb 2024 | The estimate is submitted and the tender work is going on. | Sasthamcotta WS Sn 2 HW - AE | |
| 09 Feb 2024 | The estimate is submitted and the tender work is going on. | Sasthamcotta WS Sn 2 HW - AE | |
| 05 Feb 2024 | The estimate is submitted and the tender work is going on. | Sasthamcotta WS Sn 2 HW - AE | |
| 31 Jan 2024 | The estimate is submitted and the tender work is going on. | Sasthamcotta WS Sn 2 HW - AE | |
| 27 Jan 2024 | The estimate is submitted and the tender work is going on. | Sasthamcotta WS Sn 2 HW - AE | |
| 22 Jan 2024 | The estimate is submitted and the tender work is going on. | Sasthamcotta WS Sn 2 HW - AE | |
| 18 Jan 2024 | The estimate is submitted and the tender work is going on. | Sasthamcotta WS Sn 2 HW - AE |