Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Mar 2025 • 700 mm Pile 48/48 completed • 800 mm Pile 59/59 completed • 900 mm Pile 44/44 completed • Earthwork removal for sump is in progress. • Chipping of 86 nos of pile is completed. Pile test completed on one pile and Balance work is in progress. Changanaserry PH Sn - AE
02 Mar 2025 • 700 mm Pile 48/48 completed • 800 mm Pile 59/59 completed • 900 mm Pile 44/44 completed • Earthwork removal for sump is in progress. • Chipping of 86 nos of pile is completed. Pile test completed on one pile and Balance work is in progress. Changanaserry PH Sn - AE
27 Feb 2025 • 700 mm Pile 48/48 completed • 800 mm Pile 59/59 completed • 900 mm Pile 44/44 completed • Earthwork removal for sump is in progress. • Chipping of 86 nos of pile is completed. Pile test completed on one pile and Balance work is in progress. Changanaserry PH Sn - AE
22 Feb 2025 • 700 mm Pile 48/48 completed • 800 mm Pile 59/59 completed • 900 mm Pile 44/44 completed • Earthwork removal for sump is in progress. • Chipping of 86 nos of pile is completed. Pile test completed on one pile and Balance work is in progress. Changanaserry PH Sn - AE
16 Feb 2025 • 700 mm Pile 48/48 completed • 800 mm Pile 59/59 completed • 900 mm Pile 44/44 completed • Earthwork removal for sump is in progress. • Chipping of 86 nos of pile is completed. Pile test completed on one pile and Balance work is in progress. Changanaserry PH Sn - AE
09 Feb 2025 • 700 mm Pile 48/48 completed • 800 mm Pile 59/59 completed • 900 mm Pile 44/44 completed • Earthwork removal for sump is in progress. • Chipping of 86 nos of pile is completed. Pile test completed on one pile and Balance work is in progress. Changanaserry PH Sn - AE
01 Feb 2025 • 700 mm Pile 48/48 completed • 800 mm Pile 59/59 completed • 900 mm Pile 44/44 completed • Earthwork removal for sump is in progress. • Chipping of 86 nos of pile is completed. Pile test completed on one pile and Balance work is in progress. Changanaserry PH Sn - AE
26 Jan 2025 • 700 mm Pile 48/48 completed • 800 mm Pile 59/59 completed • 900 mm Pile 44/44 completed • Earthwork removal for sump is in progress. • Chipping of 86 nos of pile is completed. Pile test completed on one pile and Balance work is in progress. Changanaserry PH Sn - AE
16 Jan 2025 • 700 mm Pile 48/48 completed • 800 mm Pile 59/59 completed • 900 mm Pile 44/44 completed • Earthwork removal for sump is in progress. • Chipping of 86 nos of pile is completed. Balance is in progress. Changanaserry PH Sn - AE
12 Jan 2025 • 700 mm Pile 48/48 completed • 800 mm Pile 59/59 completed • 900 mm Pile 44/44 completed • Earthwork removal for sump is in progress. • Chipping of pile is in progress. Changanaserry PH Sn - AE