Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
11 May 2023 | 2571 FHTC completed and pipeline laying work in progress | Punalur WS Sn - AE | |
08 May 2023 | 2571 FHTC completed and pipeline laying work in progress | Punalur WS Sn - AE | |
05 May 2023 | 2571 FHTC completed and pipeline laying work in progress | Punalur WS Sn - AE | |
02 May 2023 | 2571 FHTC completed and pipeline laying work in progress | Punalur WS Sn - AE | |
29 Apr 2023 | 2571 FHTC completed and pipeline laying work in progress | Punalur WS Sn - AE | |
27 Apr 2023 | 2571 FHTC completed and pipeline laying work in progress | Punalur WS Sn - AE | |
24 Apr 2023 | 2571 FHTC completed and pipeline laying work in progress | Punalur WS Sn - AE | |
20 Apr 2023 | 2571 FHTC completed and pipeline laying work in progress | Punalur WS Sn - AE | |
17 Apr 2023 | 2571 FHTC completed and pipeline laying work in progress | Punalur WS Sn - AE | |
13 Apr 2023 | 2571 FHTC completed and pipeline laying work in progress | Punalur WS Sn - AE |