| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 25 Sep 2026 | 50m pipe laid in Vattakkulam corporation road and is in progress | Kannur WS Sn AE 2 | |
| 14 Aug 2026 | Malikaparamba tank to kadachira road pipelaying work completed. Chamber work completed | Kannur WS Sn AE 2 | |
| 17 Jul 2026 | Malikaparamba tank to kadachira road pipelaying work completed. Chamber work completed. | Kannur WS Sn AE 2 | |
| 07 Jul 2026 | Malikaparamba tank to kadachira road pipelaying work completed. Chamber work ongoing. | Kannur WS Sn AE 2 | |
| 18 Jun 2026 | Malikaparamba tank to kadachira road pipelaying work completed. Chamber work ongoing. | Kannur WS Sn AE 2 | |
| 04 Jun 2026 | Malikaparamba tank to kadachira road pipelaying work completed. Chamber work ongoing. | Kannur WS Sn AE 2 | |
| 29 Apr 2026 | Work started. 15 meters pipe laid | Kannur WS Sn AE 2 | |
| 17 Apr 2026 | Work started. 10 meters pipe laid | Kannur WS Sn AE 2 | |
| 08 Apr 2026 | Work started. 10 meters pipe laid | Kannur WS Sn AE 2 | |
| 24 Mar 2026 | Work started. 10 meters pipe laid | Kannur WS Sn AE 2 |