Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
25 Apr 2023 | 90% completed | Irinjalakuda AE | |
03 Feb 2023 | 83% completed | Irinjalakuda AE | |
16 Dec 2022 | JJM - Kattur Grama panchayath (Part-II) - RDWSS to Karalam, Kattoor, padiyoor, Poomangalam - Providing FHTC to Rural house holds- Work in progress | Irinjalakuda AE | |
06 Dec 2022 | JJM - Kattur Grama panchayath (Part-II) - RDWSS to Karalam, Kattoor, padiyoor, Poomangalam - Providing FHTC to Rural house holds- Work in progress | Irinjalakuda AE | |
20 Oct 2022 | JJM - Kattur Grama panchayath - RDWSS to Karalam, Kattoor, padiyoor, Poomangalam - Providing FHTC to Rural house holds | Irinjalakuda AE | |
20 Oct 2022 | JJM - Kattur Grama panchayath (Part-II) - RDWSS to Karalam, Kattoor, padiyoor, Poomangalam - Providing FHTC to Rural house holds | Irinjalakuda AE | |
14 Jun 2022 | JJM - Kattur Grama panchayath - RDWSS to Karalam, Kattoor, padiyoor, Poomangalam - Providing FHTC to Rural house holds :- 568FHTC's and 6000m 50mm pvc pipe line extension completed | Irinjalakuda AE | |
02 Jun 2022 | JJM - Kattur Grama panchayath (Part-II) - RDWSS to Karalam, Kattoor, padiyoor, Poomangalam - Providing FHTC to Rural house holds: work order issued | Irinjalakuda AE | |
02 Jun 2022 | JJM - Kattur Grama panchayath - RDWSS to Karalam, Kattoor, padiyoor, Poomangalam - Providing FHTC to Rural house holds :- 568FHTC's and 6000m 50mm pvc pipe line extension completed | Irinjalakuda AE | |
29 May 2022 | JJM - Kattur Grama panchayath (Part-II) - RDWSS to Karalam, Kattoor, padiyoor, Poomangalam - Providing FHTC to Rural house holds: work order issued | Irinjalakuda AE |