Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Apr 2023 90% completed Irinjalakuda AE
03 Feb 2023 83% completed Irinjalakuda AE
16 Dec 2022 JJM - Kattur Grama panchayath (Part-II) - RDWSS to Karalam, Kattoor, padiyoor, Poomangalam - Providing FHTC to Rural house holds- Work in progress Irinjalakuda AE
06 Dec 2022 JJM - Kattur Grama panchayath (Part-II) - RDWSS to Karalam, Kattoor, padiyoor, Poomangalam - Providing FHTC to Rural house holds- Work in progress Irinjalakuda AE
20 Oct 2022 JJM - Kattur Grama panchayath - RDWSS to Karalam, Kattoor, padiyoor, Poomangalam - Providing FHTC to Rural house holds Irinjalakuda AE
20 Oct 2022 JJM - Kattur Grama panchayath (Part-II) - RDWSS to Karalam, Kattoor, padiyoor, Poomangalam - Providing FHTC to Rural house holds Irinjalakuda AE
14 Jun 2022 JJM - Kattur Grama panchayath - RDWSS to Karalam, Kattoor, padiyoor, Poomangalam - Providing FHTC to Rural house holds :- 568FHTC's and 6000m 50mm pvc pipe line extension completed Irinjalakuda AE
02 Jun 2022 JJM - Kattur Grama panchayath (Part-II) - RDWSS to Karalam, Kattoor, padiyoor, Poomangalam - Providing FHTC to Rural house holds: work order issued Irinjalakuda AE
02 Jun 2022 JJM - Kattur Grama panchayath - RDWSS to Karalam, Kattoor, padiyoor, Poomangalam - Providing FHTC to Rural house holds :- 568FHTC's and 6000m 50mm pvc pipe line extension completed Irinjalakuda AE
29 May 2022 JJM - Kattur Grama panchayath (Part-II) - RDWSS to Karalam, Kattoor, padiyoor, Poomangalam - Providing FHTC to Rural house holds: work order issued Irinjalakuda AE