Status Date |
Overall Project Status |
Project Officer |
Contact |
28 Feb 2023 |
In package 1,8%- Steel work in progress. Steining work 3rd stage completed. In package 2, 8%- 9500 m of PVC and GI 1500 m pipes are supplied. 1730 m laid. Connection work in progress. |
Malappuram Project Dn AE3 |
|
15 Feb 2023 |
In package 1, 6 % - Steel work in progress. Steining work 2nd stage completed. In package 2, 5 % - 9500 m of PVC and GI 1500 m pipes are supplied. 1130 m laid. Connection work in progress. |
Malappuram Project Dn AE3 |
|
25 Jan 2023 |
In package 1, 8500 m of PVC pipes are supplied. In Package 2, Temporary bund work completed. |
Malappuram Project Dn AE3 |
|
05 Jan 2023 |
In package 1, 8500 m of PVC pipes are supplied. package 2, Work started. |
Malappuram Project Dn AE3 |
|
20 Dec 2022 |
In package 1, 5500 m pipes supplied. Package 2, Work can be start only after the decreasing of water level in the river. |
Malappuram Project Dn AE3 |
|
12 Dec 2022 |
In package 1, 5500 m pipes supplied. Package 2, Work can be start only after the decreasing of water level in the river. |
Malappuram Project Dn AE3 |
|
16 Nov 2022 |
In package 1, Selection Notice given. Agreement not executed. In package 2, Work can be start only after the decreasing of water level in the river. |
Malappuram Project Dn AE3 |
|
28 Oct 2022 |
In package 1, Selection Notice given. Agreement not executed. In package 2, Work can be start only after the decreasing of water level in the river. |
Malappuram Project Dn AE3 |
|
18 Oct 2022 |
In package 1- Under tendering process.In package 2-Work can be start only after the decreasing of water level in the river. |
Malappuram Project Dn AE3 |
|
07 Oct 2022 |
In package 1- Under tendering process.In package 2-Work can be start only after the decreasing of water level in the river. |
Malappuram Project Dn AE3 |
|