Status Date Overall Project Status Project Officer Contact
28 Feb 2023 In package 1,8%- Steel work in progress. Steining work 3rd stage completed. In package 2, 8%- 9500 m of PVC and GI 1500 m pipes are supplied. 1730 m laid. Connection work in progress. Malappuram Project Dn AE3
15 Feb 2023 In package 1, 6 % - Steel work in progress. Steining work 2nd stage completed. In package 2, 5 % - 9500 m of PVC and GI 1500 m pipes are supplied. 1130 m laid. Connection work in progress. Malappuram Project Dn AE3
25 Jan 2023 In package 1, 8500 m of PVC pipes are supplied. In Package 2, Temporary bund work completed. Malappuram Project Dn AE3
05 Jan 2023 In package 1, 8500 m of PVC pipes are supplied. package 2, Work started. Malappuram Project Dn AE3
20 Dec 2022 In package 1, 5500 m pipes supplied. Package 2, Work can be start only after the decreasing of water level in the river. Malappuram Project Dn AE3
12 Dec 2022 In package 1, 5500 m pipes supplied. Package 2, Work can be start only after the decreasing of water level in the river. Malappuram Project Dn AE3
16 Nov 2022 In package 1, Selection Notice given. Agreement not executed. In package 2, Work can be start only after the decreasing of water level in the river. Malappuram Project Dn AE3
28 Oct 2022 In package 1, Selection Notice given. Agreement not executed. In package 2, Work can be start only after the decreasing of water level in the river. Malappuram Project Dn AE3
18 Oct 2022 In package 1- Under tendering process.In package 2-Work can be start only after the decreasing of water level in the river. Malappuram Project Dn AE3
07 Oct 2022 In package 1- Under tendering process.In package 2-Work can be start only after the decreasing of water level in the river. Malappuram Project Dn AE3