Status Date |
Overall Project Status |
Project Officer |
Contact |
27 Nov 2023 |
In package 1, 52 % - 9500 m of PVC and 1500 m GI pipes are supplied. 9812 m laid. Connections work in progress. In package 2, 46% - Steining work completed. Pipeline work in progress.
|
Malappuram Project Dn AE3 |
|
15 Sep 2023 |
In package 1, 51% - 9500 m of PVC and 1500 m GI pipes are supplied. 9812 m laid. Connections work in progress. Package 2, 46% - Steining work completed. Pipeline work in progress.
|
Malappuram Project Dn AE3 |
|
01 Aug 2023 |
In package 1, 50% - 9500 m of PVC and 1500 m GI pipes are supplied. 9812 m laid. Connections work in progress. Package 2, 45 % - Steining work completed. Pipeline work in progress.
|
Malappuram Project Dn AE3 |
|
22 Jul 2023 |
In package 1, 49% - 9500 m of PVC and 1500 m GI pipes are supplied. 9812 m laid and 400 connections provided. Package 2, 44% - Steining work completed. Pipeline work in progress.
|
Malappuram Project Dn AE3 |
|
30 Jun 2023 |
In package 1, 44%- 9500 m of PVC and 1500 m GI pipes are supplied. 9812 m laid. Connection work in progress. Package 2, 42%- Steining work completed. Pipeline work in progress.
|
Malappuram Project Dn AE3 |
|
01 Jun 2023 |
In package 1, 33% - 9500 m of PVC and 1500 m GI pipes are supplied. 6470 m laid. Connection work in progress. Package 2, 38% - Steining work completed.
|
Malappuram Project Dn AE3 |
|
03 May 2023 |
In package 1, 26%- 9500 m of PVC and 1500 m GI pipes are supplied. 5880 m laid. Connection work in progress. Package 2, 28%- Steel and shuttering work in progress. Steining work 6th stage completed.
|
Malappuram Project Dn AE3 |
|
18 Apr 2023 |
In package 1, 23%- 9500 m of PVC and GI 1500 m pipes are supplied. 5730 m laid. Connection work in progress. In package 2, 20%- Steel and shuttering work in progress. Steining work 6th stage completed.
|
Malappuram Project Dn AE3 |
|
01 Apr 2023 |
In package 1, 20%- 9500 m of PVC and GI 1500 m pipes are supplied. 4584 m laid. Connection work in progress. Package 2, 20%- Steel and shuttering work in progress. Steining work 6th stage completed. |
Malappuram Project Dn AE3 |
|
14 Mar 2023 |
In package 1, 12 %- 9500 m of PVC and GI 1500 m pipes are supplied. 2562 m laid. Connection work in progress. In package 2,. 16%-- Steel and shuttering work in progress. Steining work 6th stage completed. |
Malappuram Project Dn AE3 |
|