| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 Jun 2021 | Trial run completed on 13/6/2021. Bill submitted on 15/6/2021. | Attingal WS Dn EE | |
| 12 Jun 2021 | 99 % work completed. Trial not done due to low voltage. | Attingal WS Dn EE | |
| 03 Jun 2021 | 95% completed. | Attingal WS Dn EE | |
| 10 May 2021 | Work started and in progress. | Attingal WS Dn EE | |
| 28 Mar 2021 | Work order issued on 19-02-2021 | Attingal WS Dn EE | |
| 27 Nov 2020 | The LMR amount is equal to estimate PAC. But quoted amount is 10.5% above PAC. Contractor not willing to take up work at LMR rate. So, to be retendered | Attingal WS Dn EE | |
| 23 Nov 2020 | Under re tendering process | Attingal WS Dn EE | |
| 23 Nov 2020 | Estimate revised and resubmitted | Attingal WS Dn EE |