Status Date Overall Project Status Project Officer Contact
15 Jun 2021 Trial run completed on 13/6/2021. Bill submitted on 15/6/2021. Attingal WS Dn EE
12 Jun 2021 99 % work completed. Trial not done due to low voltage. Attingal WS Dn EE
03 Jun 2021 95% completed. Attingal WS Dn EE
10 May 2021 Work started and in progress. Attingal WS Dn EE
28 Mar 2021 Work order issued on 19-02-2021 Attingal WS Dn EE
27 Nov 2020 The LMR amount is equal to estimate PAC. But quoted amount is 10.5% above PAC. Contractor not willing to take up work at LMR rate. So, to be retendered Attingal WS Dn EE
23 Nov 2020 Under re tendering process Attingal WS Dn EE
23 Nov 2020 Estimate revised and resubmitted Attingal WS Dn EE