Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
12 Sep 2022 | No work | Parassala WS Sn | |
06 Sep 2022 | Kunnathukal Gp, Kaivankala ward - 1 site, pipe to be laid = 222m | Parassala WS Sn | |
01 Sep 2022 | Kunnathukal Gp, Kaivankala ward - 1 site, Chariyakolla ward : 1 site, pipe laid = 322.75m | Parassala WS Sn | |
30 Aug 2022 | Kunnathukal Gp, Kaivankala ward - 1 site, Chariyakolla ward - 1 site, Pipe laid = 444m | Parassala WS Sn | |
25 Aug 2022 | Kunnathukal Gp, Kottaikal ward -1 site,Kaivankala ward -1 site, Chavadi ward -1 site, pipe laid = 354m | Parassala WS Sn | |
20 Aug 2022 | Kunnathukal Gp, Kudayal ward :1, Cheriyakolla ward :1, Total = 400.5m | Parassala WS Sn | |
19 Aug 2022 | Pipe laying work started | Parassala WS Sn | |
27 Jul 2022 | Phase 2 JJM work in kunnathukal panchayat is started. Pipe laying is in progress | Neyyattinkara - JJM - AE | |
04 Jul 2022 | Phase 2 JJM work in Kunnathukal panchayat is started .Pipe laid upto date = 16154.9 m | Neyyattinkara - JJM - AE | |
25 Jun 2022 | Phase 2 JJM work in Kunnathukal panchayat is started .Pipe laid upto date = 11355.8 m | Neyyattinkara - JJM - AE |