28 Oct 2022 | Kunnathukal Gp, Karakonam ward - 1 site, 75mm upvc pipe to be laid = 12m and 32mm upvc pipe to be laid = 13.2m , Kottackal ward - 1 site, 32mm upvc pipe to be laid = 129m. | Parassala WS Sn | |
15 Oct 2022 | Kunnathukal Gp, Mooverikara ward - 1 site, 75mm upvc pipe to be laid = 15.7m and Koranamcode ward- 1 site, 32mm upvc pipe to be laid = 43m. | Parassala WS Sn | |
12 Oct 2022 | Kunnathukal Gp, Kudayal ward- 1 site, interconnection works are done. Chariyakolla ward- 1 site, interconnection works are done. Aruviyode ward - 1 site, interconnection works are done. Koranamcode ward - 1 site, 32mm upvc pipe to be laid = 30mm | Parassala WS Sn | |
06 Oct 2022 | Kunnathukal Gp, Manavari ward - 1 site , interconnection work, Koranamcode ward - 1 site, interconnection work, Kottakkal ward - 3 site, 110mm upvc pipe to be laid = 141.7m and 32mm upvc pipe to be laid = 72m | Parassala WS Sn | |
03 Oct 2022 | No work ( due to rain) | Parassala WS Sn | |
30 Sep 2022 | Kunnathukal Gp, Kottaikal ward - 2 site, 110mm upvc pipe laid = 258m and valve setting work, Manavari ward - 1site, 75mm upvc pipe laid = 9.75m and Anavoor ward - 1site, 90mm & 75mm upvc pipe laid = 11.6m | Parassala WS Sn | |
26 Sep 2022 | Kunnathukal Gp, Paliyode ward - 1 site( concrete work), Chariyakolla ward - 1 site, pipe to be laid = 216m | Parassala WS Sn | |
20 Sep 2022 | Kunnathukal Gp, Aruviyode ward - 1 site, koranamcode ward - 1 site, pipe to be laid = 345m | Parassala WS Sn | |
16 Sep 2022 | Kunnathukal Gp, Aruviyode ward - 1 site, chavadi ward- 1 site , pipe to be laid = 283.5m | Parassala WS Sn | |
13 Sep 2022 | Kunnathukal Gp, Nilamamoode ward - 1site, pipe to be laid = 202m | Parassala WS Sn |