28 Oct 2022 Kunnathukal Gp, Karakonam ward - 1 site, 75mm upvc pipe to be laid = 12m and 32mm upvc pipe to be laid = 13.2m , Kottackal ward - 1 site, 32mm upvc pipe to be laid = 129m. Parassala WS Sn
15 Oct 2022 Kunnathukal Gp, Mooverikara ward - 1 site, 75mm upvc pipe to be laid = 15.7m and Koranamcode ward- 1 site, 32mm upvc pipe to be laid = 43m. Parassala WS Sn
12 Oct 2022 Kunnathukal Gp, Kudayal ward- 1 site, interconnection works are done. Chariyakolla ward- 1 site, interconnection works are done. Aruviyode ward - 1 site, interconnection works are done. Koranamcode ward - 1 site, 32mm upvc pipe to be laid = 30mm Parassala WS Sn
06 Oct 2022 Kunnathukal Gp, Manavari ward - 1 site , interconnection work, Koranamcode ward - 1 site, interconnection work, Kottakkal ward - 3 site, 110mm upvc pipe to be laid = 141.7m and 32mm upvc pipe to be laid = 72m Parassala WS Sn
03 Oct 2022 No work ( due to rain) Parassala WS Sn
30 Sep 2022 Kunnathukal Gp, Kottaikal ward - 2 site, 110mm upvc pipe laid = 258m and valve setting work, Manavari ward - 1site, 75mm upvc pipe laid = 9.75m and Anavoor ward - 1site, 90mm & 75mm upvc pipe laid = 11.6m Parassala WS Sn
26 Sep 2022 Kunnathukal Gp, Paliyode ward - 1 site( concrete work), Chariyakolla ward - 1 site, pipe to be laid = 216m Parassala WS Sn
20 Sep 2022 Kunnathukal Gp, Aruviyode ward - 1 site, koranamcode ward - 1 site, pipe to be laid = 345m Parassala WS Sn
16 Sep 2022 Kunnathukal Gp, Aruviyode ward - 1 site, chavadi ward- 1 site , pipe to be laid = 283.5m Parassala WS Sn
13 Sep 2022 Kunnathukal Gp, Nilamamoode ward - 1site, pipe to be laid = 202m Parassala WS Sn