| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 28 Sep 2026 | Pipe laying for 4km completed and existing connection restored for 4km. Pipe supplied for phase II work. | Thaliparamba WS Section | |
| 02 Jul 2026 | Pipe laying for 4km completed and existing connection restored for 4km. Pipe supplied for phase II work. | Thaliparamba WS Section | |
| 25 Jun 2026 | Pipe laying for 4km completed and existing connection restored for 4km. Pipe supplied for phase II work. | Thaliparamba WS Section | |
| 09 Jun 2026 | Pipe laying for 4km completed and existing connection restored for 4km. Pipe supplied for phase II work. | Thaliparamba WS Section | |
| 12 May 2026 | Pipe laying for 4km completed and existing connection restored for 4km. Pipe supplied for phase II work. | Thaliparamba WS Section | |
| 24 Apr 2026 | Pipe laying for 4km completed and existing connection restored for 4km. Pipe supplied for phase II work. | Thaliparamba WS Section | |
| 07 Apr 2026 | Pipe laying for 4km completed and existing connection restored for 4km. Pipe supplied for phase II work. | Thaliparamba WS Section | |
| 27 Mar 2026 | Pipe laying for 4km completed and existing connection restored for 4km. Pipe supplied for phase II work. | Thaliparamba WS Section | |
| 13 Mar 2026 | Pipe laying for 3km completed and existing connection restored for 3km. Pipe supplied for phase II work. | Thaliparamba WS Section | |
| 04 Mar 2026 | Pipe laying for 3km completed and existing connection restored for 3km | Thaliparamba WS Section |