Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 Sep 2023 | Pipe laying: 3732.3m/190600m. HTC given today = 0 nos. Uptodated HTC 0 Nos. out of 7169. | Nattika Project Dn AE 4 | |
20 Sep 2023 | Pipe laying: 3043.3m/190600m. HTC given today = 0 nos. Uptodated HTC 0 Nos. out of 7169. | Nattika Project Dn AE 4 | |
19 Sep 2023 | Pipe laying: 2597.5m/190600m. HTC given today = 0 nos. Uptodated HTC 0 Nos. out of 7169. | Nattika Project Dn AE 4 | |
18 Sep 2023 | Pipe laying: 2333.5m/190600m. HTC given today = 0 nos. Uptodated HTC 0 Nos. out of 7169. | Nattika Project Dn AE 4 | |
17 Sep 2023 | Pipe laying: 2018m/190600m. HTC given today = 0 nos. Uptodated HTC 0 Nos. out of 7169. | Nattika Project Dn AE 4 | |
16 Sep 2023 | Pipe laying: 2018m/190600m. HTC given today = 0 nos. Uptodated HTC 0 Nos. out of 7169. | Nattika Project Dn AE 4 | |
15 Sep 2023 | Pipe laying: 1850m/190600m. HTC given today = 0 nos. Uptodated HTC 0 Nos. out of 7169. | Nattika Project Dn AE 4 | |
14 Sep 2023 | Pipe laying: 1568m/190600m. HTC given today = 0 nos. Uptodated HTC 0 Nos. out of 7169. | Nattika Project Dn AE 4 | |
13 Sep 2023 | Pipe laying: 1422m/190600m. HTC given today = 0 nos. Uptodated HTC 0 Nos. out of 7169. | Nattika Project Dn AE 4 | |
12 Sep 2023 | Pipe laying: 1122m/190600m. HTC given today = 0 nos. Uptodated HTC 0 Nos. out of 7169. | Nattika Project Dn AE 4 |