09 Nov 2023 Pipe laying: 17281.8m/190600m. HTC given today = 0 nos. Uptodated HTC 202 Nos. out of 7169. Geotagging Today:0 nos, Cumulative: 171 nos out of 7169 nos. Nattika Project Dn AE 4
06 Nov 2023 Pipe laying: 16417.8m/190600m. HTC given today = 0 nos. Uptodated HTC 202 Nos. out of 7169. Geotagging Today:0 nos, Cumulative: 171 nos out of 7169 nos. Nattika Project Dn AE 4
03 Nov 2023 Pipe laying: 15859.8m/190600m. HTC given today = 0nos. Uptodated HTC 179 Nos. out of 7169. Geotagging Today:25 nos, Cumulative: 137 nos out of 7169 nos. Nattika Project Dn AE 4
30 Oct 2023 Pipe laying: 13548.8m/190600m. HTC given today = 20nos. Uptodated HTC 159 Nos. out of 7169. Geotagging Today:20 nos, Cumulative: 92 nos out of 7169 nos. Nattika Project Dn AE 4
27 Oct 2023 Pipe laying: 12932.8m/190600m. HTC given today = 35nos. Uptodated HTC 89 Nos. out of 7169. Geotagging Today:12 nos, Cumulative: 52 nos out of 7169 nos. Nattika Project Dn AE 4
22 Oct 2023 Pipe laying: 10920.8m/190600m. HTC given today = 0 nos. Uptodated HTC 43 Nos. out of 7169. Geotagging Today:0 nos, Cumulative: 40 nos out of 7169 nos. Nattika Project Dn AE 4
19 Oct 2023 Pipe laying: 8657.8m/190600m. HTC given today = 0 nos. Uptodated HTC 43 Nos. out of 7169. Geotagging Today:0 nos, Cumulative: 40 nos out of 7169 nos. Nattika Project Dn AE 4
16 Oct 2023 Pipe laying: 7806.8m/190600m. HTC given today = 1 nos. Uptodated HTC 43 Nos. out of 7169. Geotagging Today:12 nos, Cumulative: 40 nos out of 7169 nos. Nattika Project Dn AE 4
03 Oct 2023 Pipe laying: 4776.3m/190600m. HTC given today = 0 nos. Uptodated HTC 0 Nos. out of 7169. Nattika Project Dn AE 4
02 Oct 2023 Pipe laying: 4638.3m/190600m. HTC given today = 0 nos. Uptodated HTC 0 Nos. out of 7169. Nattika Project Dn AE 4