Status Date Overall Project Status Project Officer Contact
23 Mar 2024 pipe supply today -0 m, cumulative 164136/190600 m. Today layed pipes-177 m Cumulative Pipe layed: 55713.8 /190600m. HTC given today = 12 nos. Uptodated HTC: 884 / 7169 Nos. Geotagging Today: 0Nos, Cumulative: 624 / 7169 nos , Road Restoration- Today: 0m Cumulative:875 m/190600m Nattika Project Dn AE 4
22 Mar 2024 pipe supply today -0 m, cumulative 164136/190600 m. Today layed pipes-322 m Cumulative Pipe layed: 55596.8 /190600m. HTC given today = 2 nos. Uptodated HTC: 872 / 7169 Nos. Geotagging Today: 5Nos, Cumulative: 624 / 7169 nos , Road Restoration- Today: 0m Cumulative:875 m/190600m Nattika Project Dn AE 4
21 Mar 2024 pipe supply today -0 m, cumulative 164136/190600 m. Today layed pipes-90m Cumulative Pipe layed: 55274.8 /190600m. HTC given today = 10 nos. Uptodated HTC: 870 / 7169 Nos. Geotagging Today: 0nos, Cumulative: 619 / 7169 nos , Road Restoration- Today: 0m Cumulative:875 m/190600m Nattika Project Dn AE 4
20 Mar 2024 Today layed pipes-473m Cumulative Pipe layed: 55184.8 m/190600m. HTC given today = nos. Uptodated HTC: 860 Nos. out of 7169. Geotagging Today: 0nos, Cumulative: 619 nos out of 7169 nos , Road Restoration- Today: 0m Cumulative:875 m/190600m Nattika Project Dn EE
19 Mar 2024 Pipe laying: 54711.8 m/190600m. HTC given today = nos. Uptodated HTC: 860 Nos. out of 7169. Geotagging Today: 14nos, Cumulative: 619 nos out of 7169 nos Road Restoration- Today: m Cumulative:875 m Nattika Project Dn EE
18 Mar 2024 Pipe laying: 54276.8 m/190600m. HTC given today = nos. Uptodated HTC: 860 Nos. out of 7169. Geotagging Today: 14nos, Cumulative: 619 nos out of 7169 nos Road Restoration- Today: m Cumulative:875 m Nattika Project Dn EE
17 Mar 2024 Pipe laying: 54198.8 m/190600m. HTC given today = nos. Uptodated HTC: 860 Nos. out of 7169. Geotagging Today: nos, Cumulative: 605 nos out of 7169 nos Road Restoration- Today: m Cumulative:875 m Nattika Project Dn EE
16 Mar 2024 Pipe laying: 54198.8 m/190600m. HTC given today = nos. Uptodated HTC: 860 Nos. out of 7169. Geotagging Today: 5 nos, Cumulative: 605 nos out of 7169 nos Road Restoration- Today: m Cumulative:875 m Nattika Project Dn EE
15 Mar 2024 Pipe laying: 53898.8 m/190600m. HTC given today =11 nos. Uptodated HTC: 860 Nos. out of 7169. Geotagging Today: 26 nos, Cumulative: 600nos out of 7169 nos Road Restoration- Today: m Cumulative:875 m Nattika Project Dn EE
14 Mar 2024 Pipe laying: 53346.8 m/190600m. HTC given today =5 nos. Uptodated HTC: 849 Nos. out of 7169. Geotagging Today: 11 nos, Cumulative: 574 nos out of 7169 nos Road Restoration- Today: m Cumulative:875 m Nattika Project Dn EE