03 Apr 2024 pipe supply today -0 m, cumulative 164136/190600 m. Today layed pipes = 485 m Cumulative Pipe layed: 57271.8 /190600m. HTC given today = 0 nos. Uptodated HTC: 884 / 7169 Nos. Geotagging Today: 0 Nos, Cumulative: 642 / 7169 nos , Road Restoration- Today: 0m Cumulative:875 m/190600m Nattika Project Dn AE 4
02 Apr 2024 pipe supply today -0 m, cumulative 164136/190600 m. Today layed pipes = 200 m Cumulative Pipe layed: 56786.8 /190600m. HTC given today = 0 nos. Uptodated HTC: 884 / 7169 Nos. Geotagging Today: 18 Nos, Cumulative: 642 / 7169 nos , Road Restoration- Today: 0m Cumulative:875 m/190600m Nattika Project Dn AE 4
01 Apr 2024 pipe supply today -0 m, cumulative 164136/190600 m. Today layed pipes = 171 m Cumulative Pipe layed: 56586.8 /190600m. HTC given today = 0 nos. Uptodated HTC: 884 / 7169 Nos. Geotagging Today: 0Nos, Cumulative: 624 / 7169 nos , Road Restoration- Today: 0m Cumulative:875 m/190600m Nattika Project Dn AE 4
30 Mar 2024 pipe supply today -0 m, cumulative 164136/190600 m. Today layed pipes = m Cumulative Pipe layed: 56415.8 /190600m. HTC given today = 0 nos. Uptodated HTC: 884 / 7169 Nos. Geotagging Today: 0 Nos, Cumulative: 624 / 7169 nos , Road Restoration- Today: 0m Cumulative:875 m/190600m Nattika Project Dn AE 4
29 Mar 2024 pipe supply today -0 m, cumulative 164136/190600 m. Today layed pipes = m Cumulative Pipe layed: 56415.8 /190600m. HTC given today = 0 nos. Uptodated HTC: 884 / 7169 Nos. Geotagging Today: 0Nos, Cumulative: 624 / 7169 nos , Road Restoration- Today: 0m Cumulative:875 m/190600m Nattika Project Dn AE 4
28 Mar 2024 pipe supply today -0 m, cumulative 164136/190600 m. Today layed pipes =162 m Cumulative Pipe layed: 56415.8 /190600m. HTC given today = 0 nos. Uptodated HTC: 884 / 7169 Nos. Geotagging Today: 0Nos, Cumulative: 624 / 7169 nos , Road Restoration- Today: 0m Cumulative:875 m/190600m Nattika Project Dn AE 4
27 Mar 2024 pipe supply today -0 m, cumulative 164136/190600 m. Today layed pipes =162 m Cumulative Pipe layed: 56253.8 /190600m. HTC given today = 0 nos. Uptodated HTC: 884 / 7169 Nos. Geotagging Today: 0Nos, Cumulative: 624 / 7169 nos , Road Restoration- Today: 0m Cumulative:875 m/190600m Nattika Project Dn AE 4
26 Mar 2024 pipe supply today -0 m, cumulative 164136/190600 m. Today layed pipes =378 m Cumulative Pipe layed: 56091.8 /190600m. HTC given today = 0 nos. Uptodated HTC: 884 / 7169 Nos. Geotagging Today: 0Nos, Cumulative: 624 / 7169 nos , Road Restoration- Today: 0m Cumulative:875 m/190600m Nattika Project Dn AE 4
25 Mar 2024 pipe supply today -0 m, cumulative 164136/190600 m. Today layed pipes- m Cumulative Pipe layed: 55713.8 /190600m. HTC given today = 0 nos. Uptodated HTC: 884 / 7169 Nos. Geotagging Today: 0Nos, Cumulative: 624 / 7169 nos , Road Restoration- Today: 0m Cumulative:875 m/190600m Nattika Project Dn AE 4
24 Mar 2024 pipe supply today -0 m, cumulative 164136/190600 m. Today layed pipes- m Cumulative Pipe layed: 55713.8 /190600m. HTC given today = 0 nos. Uptodated HTC: 884 / 7169 Nos. Geotagging Today: 0Nos, Cumulative: 624 / 7169 nos , Road Restoration- Today: 0m Cumulative:875 m/190600m Nattika Project Dn AE 4