| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 May 2023 | 4 th steining completed and sinking start | Kottakkal PH Sn AE | |
| 06 Apr 2023 | cube test conducted and 4 th steining concreted. | Kottakkal PH Sn AE | |
| 20 Apr 2023 | 4.5 m steining sinked | Kottakkal PH Sn AE | |
| 18 Apr 2023 | bailing out start | Kottakkal PH Sn AE | |
| 13 Apr 2023 | Third steining completed | Kottakkal PH Sn AE | |
| 11 Apr 2023 | Second staining completed | Kottakkal PH Sn AE | |
| 31 Mar 2023 | sinking started | Kottakkal PH Sn AE | |
| 23 Mar 2023 | first steining completed | Kottakkal PH Sn AE | |
| 17 Mar 2023 | First staining completed | Kottakkal PH Sn AE | |
| 13 Mar 2023 | first steining work completed | Kottakkal PH Sn AE |