| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 03 Aug 2023 | due to rain water level in kadalumdi river is high so work progress is slow.first and part bill submitted. | Tirur PH Sub Dn - AEE | |
| 03 Aug 2023 | first and part bill submited | Tirur PH Sub Dn - AEE | |
| 02 Aug 2023 | due to rain water level in kadalumdi river is high so work progress is slow. | Kottakkal PH Sn AE | |
| 31 Jul 2023 | work stopped. | Kottakkal PH Sn AE | |
| 24 Jul 2023 | work stopped. | Kottakkal PH Sn AE | |
| 19 Jul 2023 | work stopped. | Kottakkal PH Sn AE | |
| 14 Jul 2023 | work stopped. | Kottakkal PH Sn AE | |
| 12 Jul 2023 | work stopped. | Kottakkal PH Sn AE | |
| 07 Jul 2023 | work stopped due to heavy rain. | Kottakkal PH Sn AE | |
| 04 Jul 2023 | excavation ongoing | Kottakkal PH Sn AE |