| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Jun 2026 | 7 km of pipeline laid and 65 Nos of HTC given | Kannur PH Dn EE | |
| 02 Jun 2026 | 7 km of pipeline laid and 65 Nos of HTC given | Kannur PH Dn EE | |
| 25 Apr 2026 | 6.10 km of pipeline laid and HTC 23 Nos | Kannur PH Dn EE | |
| 16 Apr 2026 | 6.00 km of pipeline laid | Kannur PH Dn EE | |
| 08 Apr 2026 | 6.00 km of pipeline laid | Kannur PH Dn EE | |
| 30 Mar 2026 | 6.00 km of pipeline laid | Kannur PH Dn EE | |
| 21 Mar 2026 | 6.00 km of pipeline laid | Kannur PH Dn EE | |
| 11 Mar 2026 | 3.20 km of pipeline laid | Kannur PH Dn EE | |
| 02 Mar 2026 | 2.80 km of pipeline laid | Kannur PH Dn EE | |