Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
09 Nov 2023 Work in progress | 64% Completed | 09/11/2023 TOTAL-32.2111 KM LAID /out of 47 km , 1).90mm pvc 6kg- 21002.80m , 2}90MM 8 KG -7086.00M 3). 80mm GI- 2999.70 M, 4).110 mm pvc6kg/cm2 -1200.00m FHTC 5028/out of 6480 NOS Chittur Project Dn - AE 3
03 Nov 2023 Work in progress | 62% Completed | 03/11/2023 TOTAL-32.2025KM LAID /out of 47 km , 1).90mm pvc 6kg- 21002.80m , 2}90MM 8 KG -7000.00M 3). 80mm GI- 2999.70 M, 4).110 mm pvc6kg/cm2 -1200.00m FHTC 4747/out of 6480 NOS Chittur Project Dn - AE 3
28 Oct 2023 Work in progress | 60% Completed | 28/10/2023 TOTAL-18.854KM LAID /out of 47 km , 1).90mm pvc 6kg- 20506.80m , 2}90MM 8 KG -6767.35M 3). 80mm GI- 1352.35 M, 4).110 mm pvc -140.30m FHTC 4747/out of 6480 NOS Chittur Project Dn - AE 3
12 Oct 2023 Work in progress | 38% Completed | 12/10/2023 TOTAL-18.854KM LAID /out of 47 km , 1).90mm pvc 6kg- 18044.74m , 2}90MM 8 KG -156M 3). 80mm GI- 294 M, 4).110 mm pvc -360m FHTC 4200/out of 6480 NOS Chittur Project Dn - AE 3
07 Sep 2023 Work in progress | 36% Completed | 07/09/2023 TOTAL-18.105KM LAID /out of 47 km , 1).90mm pvc 6kg- 17906.74m , 2). 80mm GI-198M, 3).110 mm pvc -360m FHTC 3399/out of 6480 NOS Chittur Project Dn - AE 3
26 Aug 2023 Work in progress | 34% Completed | 26/08/2023 TOTAL-16.19074KM LAID /out of 47 km , 1).90mm pvc 6kg-15656.74m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 3008/out of 6480 NOS Chittur Project Dn - AE 3
15 Aug 2023 Work in progress | 33% Completed | 15/08/2023 TOTAL-15.728KM LAID /out of 47 km , 1).90mm pvc 6kg-14122.74m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 2622 Chittur Project Dn - AE 3
04 Aug 2023 Work in progress | 28% Completed | 04/08/2023 TOTAL-15.654KM LAID /out of 47 km , 1).90mm pvc 6kg-14122.00m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 2622 Chittur Project Dn - AE 3
19 Jul 2023 Work in progress | 25% Completed | 19/07/2023 TOTAL-15.654KM LAID /out of 47 km , 1).90mm pvc 6kg-13402.00m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 2374 Chittur Project Dn - AE 3
13 Jul 2023 Work in progress | 25% Completed | 13/07/2023TOTAL-15.552KM LAID /out of 47 km , 1).90mm pvc 6kg-13300.00m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 2374 Chittur Project Dn - AE 3