Status Date |
Overall Project Status |
Project Officer |
Contact |
09 Nov 2023 |
Work in progress | 64% Completed | 09/11/2023
TOTAL-32.2111 KM LAID /out of 47 km , 1).90mm pvc 6kg- 21002.80m , 2}90MM 8 KG -7086.00M 3). 80mm GI- 2999.70 M, 4).110 mm pvc6kg/cm2 -1200.00m FHTC 5028/out of 6480 NOS |
Chittur Project Dn - AE 3 |
|
03 Nov 2023 |
Work in progress | 62% Completed | 03/11/2023
TOTAL-32.2025KM LAID /out of 47 km , 1).90mm pvc 6kg- 21002.80m , 2}90MM 8 KG -7000.00M 3). 80mm GI- 2999.70 M, 4).110 mm pvc6kg/cm2 -1200.00m FHTC 4747/out of 6480 NOS |
Chittur Project Dn - AE 3 |
|
28 Oct 2023 |
Work in progress | 60% Completed | 28/10/2023
TOTAL-18.854KM LAID /out of 47 km , 1).90mm pvc 6kg- 20506.80m , 2}90MM 8 KG -6767.35M 3). 80mm GI- 1352.35 M, 4).110 mm pvc -140.30m FHTC 4747/out of 6480 NOS |
Chittur Project Dn - AE 3 |
|
12 Oct 2023 |
Work in progress | 38% Completed | 12/10/2023
TOTAL-18.854KM LAID /out of 47 km , 1).90mm pvc 6kg- 18044.74m , 2}90MM 8 KG -156M 3). 80mm GI- 294 M, 4).110 mm pvc -360m FHTC 4200/out of 6480 NOS |
Chittur Project Dn - AE 3 |
|
07 Sep 2023 |
Work in progress | 36% Completed | 07/09/2023
TOTAL-18.105KM LAID /out of 47 km , 1).90mm pvc 6kg- 17906.74m , 2). 80mm GI-198M, 3).110 mm pvc -360m FHTC 3399/out of 6480 NOS |
Chittur Project Dn - AE 3 |
|
26 Aug 2023 |
Work in progress | 34% Completed | 26/08/2023
TOTAL-16.19074KM LAID /out of 47 km , 1).90mm pvc 6kg-15656.74m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 3008/out of 6480 NOS |
Chittur Project Dn - AE 3 |
|
15 Aug 2023 |
Work in progress | 33% Completed | 15/08/2023
TOTAL-15.728KM LAID /out of 47 km , 1).90mm pvc 6kg-14122.74m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 2622 |
Chittur Project Dn - AE 3 |
|
04 Aug 2023 |
Work in progress | 28% Completed | 04/08/2023
TOTAL-15.654KM LAID /out of 47 km , 1).90mm pvc 6kg-14122.00m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 2622 |
Chittur Project Dn - AE 3 |
|
19 Jul 2023 |
Work in progress | 25% Completed | 19/07/2023
TOTAL-15.654KM LAID /out of 47 km , 1).90mm pvc 6kg-13402.00m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 2374 |
Chittur Project Dn - AE 3 |
|
13 Jul 2023 |
Work in progress | 25% Completed | 13/07/2023TOTAL-15.552KM LAID /out of 47 km , 1).90mm pvc 6kg-13300.00m , 2). 80mm GI-174M, 3).110 mm pvc -360m FHTC 2374 |
Chittur Project Dn - AE 3 |
|