Status Date Overall Project Status Project Officer Contact
12 Sep 2022 1)Package I-100% completed 2)Package II-100% completed except ROB crossing 3)Package III(a)-site levelling 4) Package III(b)- .Soil investigation completed. Land registration completed Estimate submitted for TS 5) Package IV -Transformer building construction completed at Kallisserry, Kattode & Thiruvalla panel work in progress 6) Package V- Dedicated feeder work in progress Adoor Project Dn AE3
18 Jul 2022 Clarification requested regarding additional amount claimed by KSEB Chengannur due to tender excess submitted on 17/06/2022. Reply to KSEB pending . Additional amount of Rs 1044105 demanded by KSEB. Adoor Project Dn AE3
10 Jul 2022 Clarification requested regarding additional amount claimed by KSEB Chengannur due to tender excess submitted on 17/06/2022. Reply to KSEB pending . Additional amount of Rs 1044105 demanded by KSEB. Adoor Project Dn EE
18 Jun 2022 1)Package I-100% completed 2)Package II-100% completed except ROB crossing 3)Package III(a)-site office construction in progress 4) Package III(b)- .Soil investigation completed.Land registration completed OHSR designing in progress 5) Package IV -Transformer building construction in progress at Kallisserry, Kattode & Thiruvalla 6) Package V- Dedicated feeder work in progress Adoor Project Dn EE
14 Jun 2022 1)Package I-100% completed 2)Package II-100% completed except ROB crossing 3)Package III(a)-site office construction in progress 4) Package III(b)- .Soil investigation completed.Land registration completed OHSR designing in progress 5) Package IV -Transformer building construction in progress at Kallisserry, Kattode & Thiruvalla 6) Package V- Dedicated feeder work in progress Adoor Project Dn AE3
10 Jun 2022 1)Package I-100% completed 2)Package II-100% completed except ROB crossing 3)Package III(a)-site office construction in progress 4) Package III(b)- .Soil investigation completed.Land registration completed OHSR designing in progress 5) Package IV -Transformer building construction in progress at Kallisserry, Kattode & Thiruvalla 6) Package V- Dedicated feeder work in progress Adoor Project Dn AE3
01 Jun 2022 1)Package I-100% completed 2)Package II-100% completed except ROB crossing 3)Package III(a)-site office construction in progress 4) Package III(b)- .Soil investigation completed.Land registration completed OHSR designing in progress 5) Package IV -Transformer building construction in progress at Kallisserry, Kattode & Thiruvalla 6) Package V- Dedicated feeder work in progress Adoor Project Dn AE3
24 May 2022 1)Package I-100% completed 2)Package II-100% completed except ROB crossing 3)Package III(a)-site office construction in progress 4) Package III(b)- .Soil investigation completed.Land registration completed OHSR designing in progress 5) Package IV -Transformer building construction in progress at Kallisserry, Kattode & Thiruvalla 6) Package V- Dedicated feeder work in progress Adoor Project Dn AE3
16 May 2022 1)Package I-100% completed 2)Package II-100% completed except ROB crossing 3)Package III(a)-site office construction in progress 4) Package III(b)- .Soil investigation completed.Land registration completed OHSR designing in progress 5) Package IV -Transformer building construction in progress at Kallisserry, Kattode & Thiruvalla 6) Package V- Dedicated feeder work in progress Adoor Project Dn AE2
11 May 2022 1)Package I-100% completed 2)Package II-100% completed except ROB crossing 3)Package III(a)-site office construction in progress 4) Package III(b)- .Soil investigation completed.Land registration completed OHSR designing in progress 5) Package IV -Transformer building construction in progress at Kallisserry, Kattode & Thiruvalla 6) Package V- Dedicated feeder work in progress Adoor Project Dn AE3