Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
12 Sep 2022 | 1)Package I-100% completed 2)Package II-100% completed except ROB crossing 3)Package III(a)-site levelling 4) Package III(b)- .Soil investigation completed. Land registration completed Estimate submitted for TS 5) Package IV -Transformer building construction completed at Kallisserry, Kattode & Thiruvalla panel work in progress 6) Package V- Dedicated feeder work in progress | Adoor Project Dn AE3 | |
18 Jul 2022 | Clarification requested regarding additional amount claimed by KSEB Chengannur due to tender excess submitted on 17/06/2022. Reply to KSEB pending . Additional amount of Rs 1044105 demanded by KSEB. | Adoor Project Dn AE3 | |
10 Jul 2022 | Clarification requested regarding additional amount claimed by KSEB Chengannur due to tender excess submitted on 17/06/2022. Reply to KSEB pending . Additional amount of Rs 1044105 demanded by KSEB. | Adoor Project Dn EE | |
18 Jun 2022 | 1)Package I-100% completed 2)Package II-100% completed except ROB crossing 3)Package III(a)-site office construction in progress 4) Package III(b)- .Soil investigation completed.Land registration completed OHSR designing in progress 5) Package IV -Transformer building construction in progress at Kallisserry, Kattode & Thiruvalla 6) Package V- Dedicated feeder work in progress | Adoor Project Dn EE | |
14 Jun 2022 | 1)Package I-100% completed 2)Package II-100% completed except ROB crossing 3)Package III(a)-site office construction in progress 4) Package III(b)- .Soil investigation completed.Land registration completed OHSR designing in progress 5) Package IV -Transformer building construction in progress at Kallisserry, Kattode & Thiruvalla 6) Package V- Dedicated feeder work in progress | Adoor Project Dn AE3 | |
10 Jun 2022 | 1)Package I-100% completed 2)Package II-100% completed except ROB crossing 3)Package III(a)-site office construction in progress 4) Package III(b)- .Soil investigation completed.Land registration completed OHSR designing in progress 5) Package IV -Transformer building construction in progress at Kallisserry, Kattode & Thiruvalla 6) Package V- Dedicated feeder work in progress | Adoor Project Dn AE3 | |
01 Jun 2022 | 1)Package I-100% completed 2)Package II-100% completed except ROB crossing 3)Package III(a)-site office construction in progress 4) Package III(b)- .Soil investigation completed.Land registration completed OHSR designing in progress 5) Package IV -Transformer building construction in progress at Kallisserry, Kattode & Thiruvalla 6) Package V- Dedicated feeder work in progress | Adoor Project Dn AE3 | |
24 May 2022 | 1)Package I-100% completed 2)Package II-100% completed except ROB crossing 3)Package III(a)-site office construction in progress 4) Package III(b)- .Soil investigation completed.Land registration completed OHSR designing in progress 5) Package IV -Transformer building construction in progress at Kallisserry, Kattode & Thiruvalla 6) Package V- Dedicated feeder work in progress | Adoor Project Dn AE3 | |
16 May 2022 | 1)Package I-100% completed 2)Package II-100% completed except ROB crossing 3)Package III(a)-site office construction in progress 4) Package III(b)- .Soil investigation completed.Land registration completed OHSR designing in progress 5) Package IV -Transformer building construction in progress at Kallisserry, Kattode & Thiruvalla 6) Package V- Dedicated feeder work in progress | Adoor Project Dn AE2 | |
11 May 2022 | 1)Package I-100% completed 2)Package II-100% completed except ROB crossing 3)Package III(a)-site office construction in progress 4) Package III(b)- .Soil investigation completed.Land registration completed OHSR designing in progress 5) Package IV -Transformer building construction in progress at Kallisserry, Kattode & Thiruvalla 6) Package V- Dedicated feeder work in progress | Adoor Project Dn AE3 |