Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Sep 2023 982 connections completed out of 2150(FHTC -804 and 178 htc) , 12th and Part bill submitted Vadanappilly AE
25 Sep 2023 982 connections completed out of 2150(FHTC -804 and 178 htc) , 12th and Part bill submitted Vadanappilly AE
21 Sep 2023 982 connections completed out of 2150(FHTC -804 and 178 htc) , 12th and Part bill submitted Vadanappilly AE
19 Sep 2023 982 connections completed out of 2150(FHTC -804 and 178 htc) , 12th and Part bill submitted Vadanappilly AE
18 Sep 2023 982 connections completed out of 2150(FHTC -804 and 178 htc) , 12th and Part bill submitted Vadanappilly AE
16 Sep 2023 982 connections completed out of 2150(FHTC -804 and 178 htc) , 12th and Part bill submitted. Vadanappilly AE
14 Sep 2023 982 connections completed out of 2150(FHTC -804 and 178 htc) , 12th and Part bill submitted. Vadanappilly AE
11 Sep 2023 982 connections completed out of 2150(FHTC -804 and 178 htc) , 12th and Part bill submitted. Vadanappilly AE
07 Sep 2023 982 connections completed out of 2150(FHTC -804 and 178 htc) , 12th and Part bill submitted. Vadanappilly AE
04 Sep 2023 982 connections completed out of 2150(FHTC -804 and 178 htc) , 12th and Part bill submitted. Vadanappilly AE