Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 Feb 2024 | 1133 connections completed out of 2150(FHTC-804 and 310 htc) , 13th and Part bill submitted. | Vadanappilly AE | |
14 Feb 2024 | 1133 connections completed out of 2150(FHTC-804 and 310 htc) , 13th and Part bill submitted. | Vadanappilly AE | |
06 Feb 2024 | 1133 connections completed out of 2150(FHTC-804 and 310 htc) , 13th and Part bill submitted. | Vadanappilly AE | |
22 Jan 2024 | 114 connections completed out of 2150(FHTC-804 and 310 htc) , 12th and Part bill submitted | Vadanappilly AE | |
17 Jan 2024 | 114 connections completed out of 2150(FHTC-804 and 310 htc) , 12th and Part bill submitted | Vadanappilly AE | |
11 Jan 2024 | 114 connections completed out of 2150(FHTC-804 and 310 htc) , 12th and Part bill submitted | Vadanappilly AE | |
08 Jan 2024 | 1114 connections completed out of 2150(FHTC-804 and 310 htc) , 12th and Part bill submitted | Vadanappilly AE | |
03 Jan 2024 | 982 connections completed out of 2150 ( fhtc 804 and htc 178) 12 th and part bill submitted | Vadanappilly AE | |
01 Jan 2024 | 982 connections completed out of 2150 ( fhtc 804 and htc 178) 12 th and part bill submitted | Nattika AEE | |
27 Dec 2023 | 982 connections completed out of 2150(FHTC-804 and 178 htc) , 12th and Part bill submitted | Vadanappilly AE |