Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 Feb 2022 | 692FHTCs completed out of 2150, 7th and part bill submitted | Vadanappilly AE | |
16 Feb 2022 | 691FHTCs completed out of 2150, 7th and part bill submitted | Vadanappilly AE | |
14 Feb 2022 | 691FHTCs completed out of 2150, 7th and part bill submitted | Vadanappilly AE | |
10 Feb 2022 | 685FHTCs completed out of 2150, 7th and part bill submitted | Vadanappilly AE | |
07 Feb 2022 | 685FHTCs completed out of 2150, 7th and part bill submitted | Vadanappilly AE | |
03 Feb 2022 | 685FHTCs completed out of 2150, 7th and part bill submitted | Vadanappilly AE | |
31 Jan 2022 | 685FHTCs completed out of 2150, 6th and part bill submitted | Vadanappilly AE | |
27 Jan 2022 | 679FHTCs completed out of 2150, 6th and part bill submitted | Vadanappilly AE | |
24 Jan 2022 | 679 FHTCs completed out of 2150, 6th and part bill submitted | Vadanappilly AE | |