Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 Apr 2022 | 738 FHTCs completed out of 2150, 8th and part bill submitted | Vadanappilly AE | |
24 Mar 2022 | 737 FHTCs completed out of 2150, 7th and part bill submitted | Vadanappilly AE | |
21 Mar 2022 | 730 FHTCs completed out of 2150, 7th and part bill submitted | Vadanappilly AE | |
17 Mar 2022 | 730 FHTCs completed out of 2150, 7th and part bill submitted | Vadanappilly AE | |
14 Mar 2022 | 707 FHTCs completed out of 2150, 7th and part bill submitted | Vadanappilly AE | |
11 Mar 2022 | 707 FHTCs completed out of 2150, 7th and part bill submitted | Vadanappilly AE | |
07 Mar 2022 | 695 FHTCs completed out of 2150, 7th and part bill submitted | Vadanappilly AE | |
03 Mar 2022 | 695 FHTCs completed out of 2150, 7th and part bill submitted | Vadanappilly AE | |
28 Feb 2022 | 692FHTCs completed out of 2150, 7th and part bill submitted | Vadanappilly AE | |