| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 23 Jun 2023 | 100 % work completed | Kollam WS Sn 2 - AE | |
| 20 Jun 2023 | 95 % completed, restoration of concrete work to be done. | Kollam WS Sn 2 - AE | |
| 16 Jun 2023 | 95 % completed, restoration of concrete work to be done. | Kollam WS Sn 2 - AE | |
| 12 Jun 2023 | Work started 11/6/2023 ( concrete demolishing), pipe laying works started 12/6/2023 and 25 % completed | Kollam WS Sn 2 - AE | |
| 09 Jun 2023 | Site handed over and work will start soon | Kollam WS Sn 2 - AE | |
| 05 Jun 2023 | tested pipe not get | Kollam WS Sn 2 - AE | |
| 01 Jun 2023 | tested pipe not get | Kollam WS Sn 2 - AE | |
| 29 May 2023 | tested pipe not get | Kollam WS Sn 2 - AE | |
| 24 May 2023 | tested pipe not get | Kollam WS Sn 2 - AE | |
| 22 May 2023 | tested pipe not get | Kollam WS Sn 2 - AE |