| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 19 Jul 2022 | Work completed, Final bill under preparation. | Idukki QCDL - AE | |
| 25 Mar 2022 | 80 % completed .Flooring work completed .Electrical work in progress. Painting work in progress. | Idukki QCDL - AE | |
| 25 Feb 2022 | 45% work completed .roof concrete work completed. | Idukki QCDL - AE | |
| 03 Feb 2022 | 40 % work completed. | Idukki QCDL - AE | |
| 11 Jan 2022 | 25 % completed. | Idukki QCDL - AE | |
| 10 Jan 2022 | 22% completed | Idukki QCDL - AE | |