Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Sep 2021 | Package 1 completed, package 2 - 81% completed | Kattappana AEE 1 | |
16 Sep 2021 | Package 1 completed, package 2 - 81% completed | Kattappana AEE 1 | |
03 Sep 2021 | Out of 2110 Nos FHTC, 1626 Nos provided. | Kattappana AEE 1 | |
25 Aug 2021 | Out of 2110 Nos FHTC, 1626 Nos provided. | Kattappana AEE 1 | |
13 Aug 2021 | Out of 2110 Nos FHTC, 1602 Nos provided. | Kattappana AEE 1 | |
06 Aug 2021 | Out of 2110 Nos FHTC, 1602 Nos provided. | Kattappana AEE 1 | |
03 Aug 2021 | Out of 2110 Nos FHTC, 1602 Nos provided. | Kattappana AEE 1 | |
24 Jul 2021 | Out of 2110 Nos FHTC, 1592 Nos provided. | Kattappana AEE 1 | |
19 Jul 2021 | Out of 2110 Nos FHTC, 1588 Nos provided. | Kattappana AEE 1 | |
15 Jul 2021 | Out of 2110 Nos FHTC, 1573 Nos provided. | Kattappana AEE 1 |