| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Feb 2023 | Pipe laying completed | Nedumkandam Sn AE | |
| 01 Sep 2022 | The pipes has been supplied,The PWD department has handed over the specified road to NH authorities,and they informed that the work is only possible when they start their work. | Thodupuzha PH Dn EE | |
| 24 Aug 2022 | Delay with NH issues | Thodupuzha PH Dn EE | |
| 13 Jul 2022 | The pipes has been supplied,The PWD department has handed over the specified road to NH authorities,and they informed that the work is only possible when they start their work. | Thodupuzha PH Dn EE | |
| 02 Jul 2022 | Estimate recasted | Nedumkandam Sn AE | |
| 24 Mar 2022 | Agreement executed on 19.03.2022 | Thodupuzha PH Dn EE | |
| 11 Jan 2022 | work tendered due date on 17.01.2022 | Thodupuzha PH Dn EE | |
| 29 Dec 2021 | Estimate revised | Nedumkandam Sn AE | |
| 15 Nov 2021 | Estimate Updation is under progress as per the revised rate | Nedumkandam Sn AE | |
| 05 Nov 2021 | work will re-tender after the rate revision | Thodupuzha PH Dn EE |