| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 23 Jan 2026 | Pipe Laying work completed. Measurement recorded. Final bill submitted. | Kottiyam PH Sn AE | |
| 23 Jan 2026 | Pipe Laying work completed. Measurement recorded. Final bill submitted. | Kottiyam PH Sn AE | |
| 20 Jan 2026 | Pipe Laying work completed. Measurement recorded. | Kottiyam PH Sn AE | |
| 16 Jan 2026 | Site Handed Over To The Contractor.Pipe Laying Work Completed | Kottiyam PH Sn AE | |
| 12 Jan 2026 | Site handed over to the contractor.Pipe laying work completed | Kottiyam PH Sn AE | |
| 06 Jan 2026 | Site handover to the contractor.Pipe laying work completed | Kottiyam PH Sn AE | |
| 08 Jan 2026 | Site handover to the contractor.Pipe laying work ongoing | Kottiyam PH Sn AE | |
| 06 Jan 2026 | .Site handover to the contractor.Pipe laying work ongoing | Kottiyam PH Sn AE | |
| 05 Jan 2026 | .Site handover to the contractor.pipe laying work ongoing | Kottiyam PH Sn AE | |
| 01 Jan 2026 | Work not started .Site handover to the contractor. | Kottiyam PH Sn AE |