Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Mar 2024 | Work order issued | Koothuparamba Project Sn No 1 | |
14 Mar 2024 | L1 Contractor not executed the agreement hence tender cancelled, now under retendering stage. | Koothuparamba Project Sn No 1 | |
11 Mar 2024 | L1 Contractor not executed the agreement hence tender cancelled, now under retendering stage. | Koothuparamba Project Sn No 1 | |
07 Mar 2024 | L1 Contractor not executed the agreement hence tender cancelled, now under retendering stage. | Koothuparamba Project Sn No 1 | |
04 Mar 2024 | L1 Contractor not executed the agreement hence tender cancelled, now under retendering stage. | Koothuparamba Project Sn No 1 | |
29 Feb 2024 | L1 Contractor not executed the agreement hence tender cancelled, now under retendering stage. | Koothuparamba Project Sn No 1 | |
28 Feb 2024 | L1 Contractor not executed the agreement hence tender cancelled, now under retendering stage. | Koothuparamba Project Sn No 1 | |
14 Feb 2024 | L1 Contractor not executed the agreement hence tender cancelled, now under retendering stage. | Koothuparamba Project Sn No 1 | |
02 Dec 2023 | work order issued agreement not executed | Koothuparamba Project Sn No 1 | |
17 Nov 2023 | Work order issued agreement not executed. | Koothuparamba Project Sn No 1 |