| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Jun 2025 | Work completed | Nedumkandam Sn AE | |
| 13 Feb 2025 | 100mm GL pumbing main lying works on going | Nedumkandam Sn AE | |
| 28 Jan 2025 | 100mm GI Pumping Main Laying Works On Going | Nedumkandam Sn AE | |
| 13 Jan 2025 | 100mm GI pumping main laying works continues (1902 m pipe laid) | Nedumkandam Sn AE |