Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
31 Aug 2021 | Request for PWD road restoration charges is submitted and the fund not obtained | Adoor Project Dn AE2 | |
27 Jul 2021 | Plastering of Kattamala OHSR is going on | Adoor Project Dn AE2 | |
12 Jul 2021 | compound wall construction at Kavumkazhamala is going on | Adoor Project Dn AE2 | |
01 Jul 2021 | Request for PWD road restoration charges is submitted to CE, SR vide direction on review meeting | Adoor Project Dn AE2 | |
01 Jul 2021 | Plastering works of Kavumkazhamala sump is completed | Adoor Project Dn AE2 | |
14 Jun 2021 | Structural work of Sashthamkoickal sump is completed | Adoor Project Dn AE2 | |
11 Jun 2021 | Request for PWD road restoration charges is submitted to CE, SR vide direction on review meeting | Adoor Project Dn AE2 | |
08 Jun 2021 | counter fort retianing wall structural work in Pachakge 3 is completed. | Adoor Project Dn AE2 | |
08 Jun 2021 | Last lift of Shasthamkoickal Sump is completed | Adoor Project Dn AE2 | |
03 Jun 2021 | Pipe laying cannot be started due to non remittance of PWD road cutting of 3.44 cr to PWD. | Adoor Project Dn AE2 |