31 Aug 2021 Request for PWD road restoration charges is submitted and the fund not obtained Adoor Project Dn AE2
27 Jul 2021 Plastering of Kattamala OHSR is going on Adoor Project Dn AE2
12 Jul 2021 compound wall construction at Kavumkazhamala is going on Adoor Project Dn AE2
01 Jul 2021 Request for PWD road restoration charges is submitted to CE, SR vide direction on review meeting Adoor Project Dn AE2
01 Jul 2021 Plastering works of Kavumkazhamala sump is completed Adoor Project Dn AE2
14 Jun 2021 Structural work of Sashthamkoickal sump is completed Adoor Project Dn AE2
11 Jun 2021 Request for PWD road restoration charges is submitted to CE, SR vide direction on review meeting Adoor Project Dn AE2
08 Jun 2021 counter fort retianing wall structural work in Pachakge 3 is completed. Adoor Project Dn AE2
08 Jun 2021 Last lift of Shasthamkoickal Sump is completed Adoor Project Dn AE2
03 Jun 2021 Pipe laying cannot be started due to non remittance of PWD road cutting of 3.44 cr to PWD. Adoor Project Dn AE2