| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 26 Mar 2022 | 1976 FHTCs out of 2000 completed and bill for 1976 FHTCs submitted .Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval | Kallara AE | |
| 24 Mar 2022 | 1976 FHTCs out of 2000 completed and bill for 1890 FHTCs submitted .Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval | Kallara AE | |
| 22 Mar 2022 | 1890FHTCs out of 2000 completed and bill for 1890 FHTCs submitted .Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval | Kallara AE | |
| 21 Mar 2022 | 1890FHTCs out of 2000 completed and bill for 1890 FHTCs submitted .Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval | Kallara AE | |
| 19 Mar 2022 | 1890FHTCs out of 2000 completed and bill for 1890 FHTCs submitted .Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval | Kallara AE | |
| 17 Mar 2022 | 1890FHTCs out of 2000 completed and bill for 1890 FHTCs submitted .Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval | Kallara AE | |
| 15 Mar 2022 | 1819 FHTCs out of 2000 completed and bill for 1779 FHTCs submitted .Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval | Kallara AE | |
| 14 Mar 2022 | 1819 FHTCs out of 2000 completed and bill for 1779 FHTCs submitted .Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval | Kallara AE | |
| 11 Mar 2022 | 1819 FHTCs out of 2000 completed and bill for 1779 FHTCs submitted .Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval | Kallara AE | |
| 09 Mar 2022 | 1819 FHTCs out of 2000 completed and bill for 1779 FHTCs submitted .Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval | Kallara AE |