Overall Project Status

Status Date Overall Project Status Project Officer Contact
09 May 2022 2045 FHTCs completed. Some connections need to be completed in PWD roads which already given and interconnection pending Kallara AE
07 May 2022 2045 FHTCs completed. Some connections need to be completed in PWD roads which already given and interconnection pending. Kallara AE
03 May 2022 2045 FHTCs completed. Some connections need to be completed in PWD roads which already given and interconnection pending. Kallara AE
29 Apr 2022 2045 FHTCs completed. Some connections need to be completed in PWD roads which already given and interconnection pending. Kallara AE
26 Apr 2022 2045 FHTCs completed. Some connections need to be completed in PWD roads which already given and interconnection pending. Kallara AE
25 Apr 2022 2045 FHTCs completed. Some connections need to be completed in PWD roads which already given and interconnection pending. Kallara AE
23 Apr 2022 2045 FHTCs completed. Some connections need to be completed in PWD roads which already given and interconnection pending. Kallara AE
21 Apr 2022 2045 FHTCs completed. Some connections need to be completed in PWD roads which already given and interconnection pending. Kallara AE
19 Apr 2022 2045 FHTCs completed. Some connections need to be completed in PWD roads which already given and interconnection pending. Kallara AE
18 Apr 2022 2000 FHTCs out of 2000 completed and bill for 1976 FHTCs submitted .Pipe laying work going on .Request for testing pipe has been submitted also revised estimate submitted for approval Kallara AE