Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Feb 2023 75 mm PVC-14076m,63 mm PVC-11058m,50 mm PVC-4026 m Pipe supplied . Pipe laying in progress. Nattika Project Dn AE 6
01 Feb 2023 75 mm PVC-14076m,63 mm PVC-11058m,50 mm PVC-4026 m Pipe supplied . Pipe laying in progress. Nattika Project Dn AE 6
31 Jan 2023 75 mm PVC-14076m,63 mm PVC-11058m,50 mm PVC-4026 m Pipe supplied . Pipe laying in progress. Nattika Project Dn AE 6
30 Jan 2023 75 mm PVC-14076m,63 mm PVC-11058m,50 mm PVC-4026 m Pipe supplied . Pipe laying in progress. Nattika Project Dn AE 6
29 Jan 2023 75 mm PVC-14076m,63 mm PVC-11058m,50 mm PVC-4026 m Pipe supplied . Pipe laying in progress. Nattika Project Dn AE 6
28 Jan 2023 75 mm PVC-14076m,63 mm PVC-11058m,50 mm PVC-4026 m Pipe supplied . Pipe laying in progress. Nattika Project Dn AE 6
28 Jan 2023 75 mm PVC-14076m,63 mm PVC-11058m,50 mm PVC-4026 m Pipe supplied . Pipe laying in progress. Nattika Project Dn AE 6
27 Jan 2023 75 mm PVC-14076m,63 mm PVC-11058m,50 mm PVC-4026 m Pipe supplied . Pipe laying in progress. Nattika Project Dn AE 6