Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
06 Jun 2021 | 2316fhtc given | Kollam Project Dn AE | |
03 Jun 2021 | 2286 fhtc given | Kollam Project Dn AE | |
02 Jun 2021 | 2264 fhtc given | Kollam Project Dn AE | |
02 Jun 2021 | 2231 fhtc given | Kollam Project Dn AE | |
29 May 2021 | 2169 fhtc given | Kollam Project Dn AE | |
28 May 2021 | 2169 fhtc given | Kollam Project Dn AE | |
27 May 2021 | 2129 nos given | Kollam Project Dn AE | |
25 May 2021 | 2117 fhtc given | Kollam Project Dn AE | |
23 May 2021 | Work has been stopped due to triple lockdown imposed in Thrikkovilvattom gp from 20-5-2021 | Kollam Project Dn AE | |
21 May 2021 | Work has been stopped due to triple lockdown imposed in Thrikkovilvattom gp from 20-5-2021 | Kollam Project Dn AE |