Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
28 Jul 2021 | Total FHTC given 2905 | Kollam Project Dn AE | |
24 Jul 2021 | 2890 fht c given | Kollam Project HD | |
19 Jul 2021 | no connection reported due to geotag site issue | Kollam Project HD | |
08 Jul 2021 | 2777 fhtc given | Kollam Project Dn AE | |
23 Jun 2021 | 2543 fhtc given | Kollam Project Dn AE | |
22 Jun 2021 | 2543 fhtc given | Kollam Project Dn AE | |
22 Jun 2021 | 2543 fhtc given | Kollam Project Dn AE | |
17 Jun 2021 | 2513 fhtc given | Kollam Project Dn AE | |
13 Jun 2021 | 2417 FHTC GIVEN | Kollam Project Dn AE | |
10 Jun 2021 | 2376 FHTC GIVEN | Kollam Project Dn AE |