Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Sep 2025 105 connections replaced, chamber work completed and one interconnection work remaining. Perlasserry Sn 1
29 Aug 2025 one chamber work and one interconnection work remaining. Perlasserry Sn 1
21 Aug 2025 one chamber work and one interconnection work remaining. Perlasserry Sn 1
14 Aug 2025 105 connections replaced. Perlasserry Sn 1
08 Aug 2025 105 connections replaced. Perlasserry Sn 1
02 Aug 2025 Out of 105 connections,102 connections replaced. Perlasserry Sn 1
28 Jul 2025 Out of 105 connections,102 connections replaced. Perlasserry Sn 1
16 Jul 2025 Out of 105 connections, 85 connections replaced. Perlasserry Sn 1
10 Jul 2025 Out of 105 connections, 85 connections replaced. Perlasserry Sn 1
02 Jul 2025 Pipe laying completed(2 kms) Perlasserry Sn 1