13 Nov 2025 105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining. Perlasserry Sn 1
06 Nov 2025 105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining. Perlasserry Sn 1
01 Nov 2025 105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining. Perlasserry Sn 1
28 Oct 2025 105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining. Perlasserry Sn 1
22 Oct 2025 105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining. Perlasserry Sn 1
16 Oct 2025 105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining. Perlasserry Sn 1
03 Oct 2025 105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining. Perlasserry Sn 1
26 Sep 2025 105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining. Perlasserry Sn 1
23 Sep 2025 105 connections replaced, chamber work completed, interconnection work completed and road restoration work remaining. Perlasserry Sn 1
12 Sep 2025 105 connections replaced, chamber work completed and one interconnection work remaining. Perlasserry Sn 1